The model workflow dictates in what chronological order the model work orders need to be scheduled, and which model work orders are restricted by other model work orders.
Go to the navigation menu and then click on Models.
Select the model and then click on the Workflow tab.
Drag and drop the work orders from the Unrestricted Work Orders section to the workflow workspace in the order that they should be completed. To automatically connect the two arrows, drag the work order over so that it is directly on top of the previous work order.
To edit the connection between the two work orders, click on the arrow that connects them. Then click on the pencil icon to edit.
Select the Type. FS is finish to start which indicates the previous work order needs to complete before the next one can be started. SS is start to start which indicates that both work orders can be started at the same time. If a lag day is needed between two work orders, enter the number of days in the lag field. Then click on Save.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article