When I'm setting up my Bid Required Days and PO Approval Days, do those numbers get added together?

Modified on Tue, 24 Mar at 10:33 AM

No. Those numbers do not get added together, therefore, you'll always want your Bid days to be greater than your PO Approval days.


  • Submit Bid Req Days - The number of days before the start of a work order that the bid is required.
  • PO Approval Days - The number of days before the start of a project that you want to start showing checklist items.